The Mayor’s Office issued the following updates on current roadwork projects.
Mid-City Group A
During January, Hard Rock Construction Co. crews completed paving work on various blocks in the $6.3 million Mid-City Group A infrastructure improvement project. The completion of these areas accounted for 92 percent of the originally contracted paving work. Crews continue street rehabilitation work and are expected to begin sewer line work later this month based upon the findings of recent closed-circuit television testing.
Bayou St. John, Fairgrounds, 7th Ward Group B
City officials visited Bayou St. John, Fairgrounds, Seventh Ward Group B’s LePage Street to break ground on the $23 million infrastructure improvement project on Jan. 21. During January, Barriere construction crews began drainage work and are expected to begin test closures in preparation for future water line tie-ins next month. Crews are also working on roadway and sidewalk restoration.
Rain gardens are part of the Hagan Lafitte drainage project. (Roadwork NOLA)
Hagan Lafitte drainage project
Command Construction Industries crews are wrapping up construction and paving on all major streets that border the Hagan Lafitte Drainage project. Rain gardens have been planted throughout St. Peter and Toulouse streets to help absorb excessive rainwater. The $7.1 million Hagan-Lafitte project is a “gray-green” infrastructure project that features upsized drainage, urban bioswales and a huge water storage facility located underneath Easton Park. It is scheduled to be complete this winter.
City Park Group A
On Dec. 29, city leaders kicked off the City Park Group A infrastructure improvement project on Dumaine Street. Fleming Construction Co. crews have completed main sewer line replacements in the 4000 block of Delgado Street. Crews continue to work on main sewer line replacements on the 800 block of Roosevelt Street. New sidewalks have been installed on St. Peters Street, which includes Americans with Disabilities Act-compliant curb ramps at intersections. Crews will start sewer and water line system replacements and full-depth roadway reconstruction on St. John Court. All residents will be informed ahead of any construction work that will involve utility disruption and / or impact their parking and access to their street and driveways.
Navarre Group A
In January, crews from Hard Rock Construction Co. began installing new concrete curbs and gutters along Central Park and East Park Place, and the wearing course (one of the final layers of roadway restoration) of asphalt was laid on North Park and Middle Park Place. Overall the project is more than 70 percent complete.
The coronavirus restrictions prevented the City Council from holding a hearing on Carnival safety planned for the March meeting of the Emergency Preparedness and Cybersecurity Special Committee, established in response to multiple tragic events that occurred in the past year.
from the City of New Orleans New Orleans officials released the following information following heavy rains and thunderstorms that moved through the metro area Sunday morning. More than five inches of rain fell in parts of the city between 11 p.m. and 6 a.m., with bouts of heavy rain at rates of two inches an Read More…
Seth Bloom and Jay H. Banks placed first and second, respectively, out of the field of six candidates for the open District B seat on the New Orleans City Council, sending them to a runoff next month, according to the results of voting in Saturday’s election.